Anglo-Suisse – WD 117 Development Project ImageDesign consultation, project management and inspection associated with the WD 117-H jacket, deck and pipelines. Project consisted of fabrication of one (1) 4-pile jacket installed in a water depth of 201′, refurbishment and installation of deck and equipment needed to support multiple wells flowing back to nearby processing platform. Installation of three (3) 6″ infield flow lines each one (1) mile in length, one (1) mile 6″ gas export pipeline, and one (1) three (3) mile 10″ oil export pipeline.

Project Management Scope of Work:

  • Perform all project bidding and evaluating to include engineering, fabrication and installation
  • Design engineering consultation and management of all contract engineering work required
  • Manage procurement of all materials used in fabrication and construction activities
  • Manage fabrication and installation activities by all contractors
  • Assemble complete project documentation

Inspection Scope of Work:

  • Inspect materials as needed at various fabrication yards
  • Inspect fabrication of jacket
  • Inspect refurbishment of deck and facilities
  • Inspection of structure installation and hookup activities
  • Inspection for all pipeline installation and commissioning activities
  • Gather data for assembly of project job books