Enbridge Energy – Zybach Plant Shutdown

Enbridge Energy – Zybach Plant Shutdown

Project Details & RCI Activities:


Project Date: June 2007
Location: Zybach, Texas

RCI’s team was instrumental in planning and executing a planned shutdown of the facility to facilitate various maintenance operations. Due to the nature of the shutdown reducing downtime and safe execution of the planned activities were critical to Enbridge. RCI provided both project management and inspection of the above activities on location and out of our Morgan City office. Through effective management of this project RCI assisted in minimizing the shutdown to only seven (7) days for Enbridge. Once the facility was shutdown and purged of product RCI managed:

  • Removal and replacement of several reboilers and heaters
  • Cleaning of the gas exchangers and associated piping
  • Maintenance of, and replacement, components on the turbo expanders and mole sieves
  • Replacement of the NGL pump and multiple motors and actuators on several compressors

Project Management Scope of Work:

  • Overall project planning and scheduling
  • Field management at location
  • Pre-commissioning and commissioning oversight

Inspection Scope of Work

  • Fabrication and construction inspection
  • Material expediting
Contact us

RCI Energy Group

Providing a complete project management team for your project or an expert for your specific need.

Learn More

Contact Us

Have a question? Call or email us for more information.

Get In Touch

Employment

RCI is interested in qualified individuals that meet the RCI excellence minimums.

See Current Openings
Share by: